| Number/Bid Sheet |
Project Description |
Advertised |
Bid Opened |
Type |
| 29485A-2012-1 |
County Center Drive Bus Stop Improvements |
May 2, 2012 |
May 22, 2012 @ 10:00am |
IFB |
757-5983 (revised) |
Construction of Module 4 LFG Well Installation at the Neal Road Recycling and Waste Facility |
April 16, 2012 |
May 11, 2012 @ 11:00 am |
IFB |
| 18491-2012-1 |
Lincoln Boulevard Median Modifications |
April 19, 2012 |
May 8, 2012 @ 10:00 am |
IFB |
| 42071-97-1 |
Ord Ferry Road Bridge Seismic Retrofit at Sacramento River Federal Bridge Replacement Project |
April 2, 2012 |
April 25, 2012 @ 10:00 am |
IFB |
| N/A |
Concow Area Infrastructure Improvement Project |
|
Nov 21, 2011 @ 4:00 PM |
RFP |
| N/A |
2011 Casner Orrick Site 757-75715 |
|
Oct 27, 2011 @ 3:00 PM |
RFP |
| 757-5863 |
Storm Water Basin No. 2 |
August 2, 2011 |
Aug 22, 2011 @ 11:00 AM |
IFB |
| 48203-2007-1 |
Rehabilitation of Hegan Lane from the UPRR Tracks to the Midway |
Feb. 21, 2011 |
March 16, 2011 @ 10:00 am |
IFB |
| 18491-2008-1 |
Lincoln Boulevard Median Improvement Project |
Dec. 9, 2010 |
January 6, 2011 @ 1:30 pm |
IFB |
| 18491-2009-1 |
Lincoln Boulevard Median Landscaping Project |
Dec. 9, 2010 |
January 6, 2011 @ 2:00 pm |
IFB |
| 23521-2007-1 |
The Construction of Lower Wyandotte Road and Monte Vista Avenue SRTS Project |
|
July 29, 2010 |
IFB |
| 757-5917 |
Re-Bid of the Construction of Module 4, Phase D Base Liner |
|
July 12, 2010 |
IFB |
| 10661-2009-1 |
Oro Bangor Hwy Rehabilitation |
|
June 29, 2010 |
IFB |
File 560.1.2 |
Request for Quote for Aerial Survey of Neal Road Recycling and Waste Facility |
|
May 21, 2010 |
RFQ |
| N/A |
Neal Road Recycling and Waste Facility Solid Waste Management System |
|
April 9, 2010 |
RFP |
| TSR 10-01 |
Tree and Stump Removal 2010-01 |
March 17, 2010 |
April 7, 2010 |
RFQ |
| NRRWF-EMR-1001 |
Environmental Monitoring and Reporting for the NRRWF |
|
November 10, 2009 |
RFP |
| NRRWF-ODOF-0901 |
Oil Drop-off Facility - City of Biggs Corporate Yard |
|
September 24, 2009 |
RFQ |
| 50255C-2005-1 |
The Construction of SR 99 Frontage Road |
July 23, 2009 |
August 20, 2009 |
IFB |
| AC-2009-1 |
Overlay of Midway from Richvale Highway to the Western Canal Bridge |
July 9, 2009 |
August 6, 2009 |
IFB |
| 04451-09-1 |
Overlay of Lower Honcut from SR 70 to Palermo Honcut Highway |
July 9, 2009 |
August 5, 2009 |
IFB |
| 757-75713 |
Landfill Gas Compliance Well Installation |
June 30, 2009 July 6, 2009 |
July 14, 2009 |
IFB |
| BWBS 09-01 |
RFQ Black Walnut Burl Sale 2009-01 |
|
June 3, 2009 |
RFQ |
| TSR 09-01 |
Tree and Stump Removal 2009-01 |
May 6, 2009 |
May 20, 2009 |
RFQ |
| 757-5916 |
Excavation of Module 4, Phase D at the Neal Road Sanitary Landfill |
March 17, 2009 |
April 7, 2009 |
IFB |
| 757-4953 |
DESIGN, ENGINEERING, PERMITTING ASSISTANCE, PREPARATION OF BID DOCUMENTS FOR DIVERSION/RECYCLING, TRANSFER AND ASSOCIATED FACILITIES – NEAL ROAD LANDFILL |
|
Dec. 17, 2008 |
RFP |
| 757-5925 |
VADOSE ZONE WELLS, NEAL ROAD LANDFILL, COUNTY PROJECT |
|
March 21, 2008 |
RFP |
| 757-5915 |
The Development of a Landfill Gas Utilization Project at the Butte County Neal Road Landfill |
|
Jan 25, 2008 |
RFP |
| 51261-2-2005-1 |
Construction of Skyway Lookout Point Parking and Pedestrian Viewing Facility |
May 21, 2008 |
June 12, 2008 |
IFB |
| 51261-1-06-1 |
Construction of Skyway & Honey Run Road Signalization |
May 6, 2008 |
June 4, 2008 |
IFB |
| 16321-07-1 |
Riceton Highway Overlay From Afton Road to the U.P.R.R. Tracks |
April 17, 2008 |
May 13, 2008 |
IFB |
| 51261-07-1 |
Overlay of the Skyway Chico-Bound Lanes |
April 15, 2008 |
May 9, 2008 |
IFB |
| 43341-06-1 |
Construction of Durham-Pentz Road & Butte Campus Drive Signalization |
April 1, 2008 |
April 23, 2008 |
IFB |
| 23201-95-1 |
Aguas Frias Road Bridge across Butte Creek Federal Bridge Replacement Project |
March 19, 2008 |
April 10, 2008 |
IFB |
| 757-5903 |
Construction Quality Assurance Monitoring for Construction of Module 4, Phase C, Neal Road Sanitary Landfill |
May 4, 2007 |
May 25, 2007 |
RFP |
| 44201-02-1 |
Durham-Dayton Highway Bridge across Hamlin Slough |
November 20, 2007 |
December 12, 2007 |
IFB |
| 757-5903 |
Construction of Module 4, Phase C, Neal Road Sanitary Landfill |
April 30, 2007 |
May 23, 2007 |
IFB |
| SC-2007-1 |
2007 Scrub Seal/Micro-Surfacing Project |
April 17, 2007 |
May 15, 2007 |
IFB |
| 757-5861 |
Septage Sludge and Solids Removal |
|
March 11, 2007 |
RFP |
| 21461-98-2 |
Ophir Rd and Lincoln Blvd Signalization |
March 2, 2007 |
March 28, 2007 |
IFB |
| 757-5879 |
Evacation of Module 4, Phase C at the Neal Road Sanitary Landfill |
N/A |
January 03, 2007 |
IFB |
| 3829 |
Lower Honcut Road Bridge Painting across Wyandotte Creek |
May 3, 2006 |
May 25, 2006 |
IFB |
| 3825 |
Oro-Bangor Highway Bridge Painting across Rocky Honcut Creek |
May 3, 2006 |
May 25, 2006 |
IFB |
| 5857 |
Phase 2 Closure of Modules 1 and 3 - Neal Rd Sanitary Landfill |
March 10, 2006 |
April 5, 2006 |
IFB |
| 61165A |
Reconstruction of a portion of Garner Ln. |
June 16, 2005 |
July 14, 2005 |
IFB |
| 5847 |
Construction of Module 4, Phase B at the Neal Road Sanitary Landfill |
March 1, 2005 |
March 30, 2005 |
IFB |
| 30142 |
Partial Rehabilition of Seven Mile Lane |
Sept 7, 2004 |
Sept 28, 2004 |
IFB |
| 3828 |
Lower Honcut Road Bridge Painting Project |
May 26, 2004 |
June 17, 2004 |
IFB |
| 757-5820 |
Construction of the Leachate impoundment and sesdimentation basin at the Neal Road Sanitary Landfill. |
May 10, 2004 |
May 25, 2004 @ 11:00 AM |
IFB |
| 42253-01-1 |
Insallation of Storm Drain facilies along and partial reconstruction of Holland Ave |
April 30, 2004 |
May 21, 2004 @ 11:00 AM |
IFB |
| 757-5808 |
Module 4 Access Road at Neal Road Lanfill |
August 8, 2003 |
August 29, 2003 @ 11:00 A.M. |
IFB |
| 56171-96-1 |
Reconstruction of West East Avenue From SR 32 to Chico City Limit Line |
July 15, 2003 |
August 5, 2003 @ 10:00 A.M. |
IFB |
| 757-5803 |
Partial Final Closure Modules 1, 2 and 3 Neal Road Sanitary Landfill |
07/01/2003 |
07/25/2003 |
IFB |
| 16182 |
Afton Road Bridge Painting - Removing existing paint and corrosion and apply new paint and coatings. |
03/28/2003 |
06/19/2003 |
IFB |
| 51261 |
Rehabilitation of Skyway from Chico City Limits to approx. 6.25 miles east. |
05/16/2003 |
06/06/2003 |
IFB |
| 5799 |
Construction of Module 4, Phase A, at the Neal Road Sanitary Landfill |
03/07/2003 |
04/04/2003 |
IFB |
| 820 |
Neal Road Sanitary Landfill - excavation of module 4, phase A
|
06/24/2002 |
07/15/2002 |
IFB |
| 2175 |
Reconstruction of Oak Lawn Ave. |
06/18/2002 |
07/18/2002 |
IFB |
| 814 |
Installation of sanitary sewer facilities at various locations on Oak Lawn Ave. |
06/12/2002 |
06/24/2002 |
IFB |
| 2204 |
Palermo Rd Rehabilitation - from Railroad Ave to Upper Palermo Rd |
04/23/2002 |
05/13/2002 |
IFB |
| 3808 |
Construction of West Sacramento Ave Bridge across Kusal Slough |
04/15/2002 |
05/06/2002 |
IFB |
| 3793 |
Construction of Centerville Road Bridge across Butte Creek |
03/21/2001 |
05/08/2001 |
IFB |